SUMMARY OF PROPOSED 2022/23 LOCAL TRANSPORT PLAN [LTP] CAPITAL PROGRAMME NEW ALLOCATIONS

 

Project/

Programme

Description

(see Footnotes below for explanation of symbols) 

2022/23 Proposed New

Allocation (£’000s)

CAPITAL RENEWAL/MAINTENANCE

Maintaining links and routes to improve………….

Surfaces

Roads #

400

 

Pavement/Footways

350

Drainage

Replacement of failed gullies/soakaways

175

Street Lighting

Replacement of connections and columns @

300

Bridges & Structures

Retaining Walls

175

 

Seafront Highway Arches Renewal Programme

 

 

Phases 3 & 4 design - King’s Road

250

 

Arch 181

180

 

Duke’s Mound Arches

300

Highway Asset Management

Surveys/update inventory/strategy evidence

50

CAPITAL RENEWAL/MAINTENANCE SUB-TOTAL

2,180

   

INTEGRATED/SUSTAINABLE TRANSPORT

Connecting people with……….

Education, Training & Learning

School Streets

150

 

School Travel Plan Measures *

10

SUB-TOTAL

160

Workplaces & job opportunities

Business Travel Plan Measures *

20

 

Personalised Travel Planning *

10

SUB-TOTAL

30

Parks, open spaces & the National Park

Rights of Way Improvement Programme

50

SUB-TOTAL

50

Interchanges

Cycle parking

10

 

Motorcycle parking

10

 

Accessible bus-stops

50

SUB-TOTAL

70

Improving neighbourhoods with……….

Road Safety measures

Collision/casualty/speed reduction sites

150

SUB-TOTAL

150

Air Quality measures

Electric vehicle charging points

50

 

SUB-TOTAL

continued……………./

50

Active travel measures

Pedestrian crossings – freestanding sites

225

 

Walking network – incl. dropped kerbs and handrails

100

 

Cycle network/Active Travel Fund Tranche 1 & 2 works

900

 

SUB-TOTAL

1,225

Managing links and routes with……….

Technology & Travel Information

‘Intelligent/smart’ Traffic Signals

300

SUB-TOTAL

300

Connecting people and neighbourhoods with, and improving, the ..............

City Centre & Seafront

Valley Gardens:Phases 1 & 2 – completion

50

 

Valley Gardens:Phase 3 – detailed design and construction **

0

 

Bus Network Infrastructure

200

SUB-TOTAL

250

General allocations

‘Section 106’ works

Various sites +

50

Minor works

Scheme completion & scoping/Monitoring

23

SUB-TOTAL

73

INTEGRATED/SUSTAINABLE TRANSPORT SUB-TOTAL

2,358

TOTAL LTP ALLOCATIONS

4,538

 

 

Overall funding and budgetary sources/decisions for allocations:-

 

Government Funding

 

LTP Integrated Transport Block Grant Allocation

3,083

LTP Maintenance Block Grant Allocation

1,455

Highway Maintenance Incentive Fund (based on Band 3 assessment)

364

Pothole funding

1,455

SUB-TOTAL

6,357

Council Funding

 

Street lighting ‘Invest to Save’

2,000

Seafront heritage lighting renewal programme

250

Brighton Bikeshare Replacement Programme

704

Strategic Transport Model

500

SUB-TOTAL

3,454

Local Enterprise Partnership [LEP]

 

Local Growth Fund – Valley Gardens Phase 3

1,455

SUB-TOTAL

1,455

GRAND TOTAL

11,266

 

Footnotes

#- sum will be increased through addition of Government Incentive Funding allocation (£364,000 based on Band 3 self-assessment ranking) and Pothole funding (£1.455m).

 

@- committed contribution to ‘Invest to Save’ project (PR&G Committee – 8/2/16).

 

+- to enable design and delivery of works associated with approved development.

 

* - local contribution to support DfT-funded Capability Fund projects, subject to confirmation of funds

 

** - local contribution not required in 2022/23 - funded by LEP Local Growth Fund.

 

 

 

NOTES

·      In many cases, costs indicated within the proposed programme are preliminary estimates. 

·      Expenditure on schemes may need to be increased, reduced or deferred during a financial year as information becomes available, such as survey results, tender returns or unforeseen engineering difficulties. 

·      The timing of construction works may be subject to network co-ordination with other council projects, development, utility companies, contractor availability and weather conditions.